June, 2022: Masukutse Community Spring Protection Complete!
Masukutse Community now has access to clean water! We transformed Joshua Makavila Spring into a flowing source of naturally filtered water thanks to your donation. Our team also trained the community on improved sanitation and hygiene practices. Together, these components will unlock the opportunity for community members to live better, healthier lives.
Happy community members!
Farmer Alice Siranjero, 48, said, "Access to clean and safe water has positively impacted me in a great way in that my children are no longer absent from school due to dirty uniforms or sickness caused by unsafe water. I can fetch water for other people in return for money thus getting a living."
Alice collecting water.
Children were just as excited as adults about the new waterpoint.
"Access to clean water has drastically improved my life in that I can wash clothes at least twice a week, and bathe daily. It will also reduce the cost of seeking medication which will aid my parents in doing development projects," said Joan V., 14. "As a child and a star in my school, my focus will be concentrating on studies and ensuring my star shines."
Joan collects water with a big smile.
Preparing for Spring Protection
Community members worked together to source and carry all locally available construction materials to the spring. These included bricks, sand, stones, and fencing poles. Some people also chiseled away at large rocks to break them down into gravel. Because people have to carry most items by hand, the material-collection process can take anywhere from a few weeks to months.
Community members preparing construction materials.
When the community was ready, we sent a lorry to deliver the remaining construction materials, including cement, plastic tarps, and hardware. Then, our construction artisan and field officers deployed to the spring to begin work. Individual households provided meals throughout each day to sustain the work team.
From Open Source to Protected Spring: A Step-by-Step Process
At last, it was time to dig in at the spring! Locals lent their strength to the artisans to help with the manual labor.
Excavation.
First, we cleared and excavated the spring area. Next, we dug a drainage channel below the spring and several runoff diversion channels above and around the spring. These help to divert surface contaminants away.
To ensure community members could still access water throughout the construction process, we also dug temporary channels from the spring's eye around the construction site. This allowed water to flow without disrupting community members' tasks or the construction work.
Foundation.
Excavation created space for setting the spring's foundation, made of thick plastic tarp, wire mesh, concrete, and waterproof cement. After establishing the base, we started brickwork to build the headwall, wing walls, and stairs.
Setting the discharge pipe.
Once the walls had grown tall enough, we began one of the most crucial steps: setting the discharge pipe. The discharge pipe needs to be positioned low enough in the headwall so the water level never rises above the spring's eye, yet high enough to allow room for the average jerrycan (a 20-liter container) to sit beneath the pipe without making contact.
If we place the discharge pipe too high above the spring's eye, backpressure could force water to emerge elsewhere. Too low, and community members would not be able to access the water easily. We embedded the pipe using clay (or mortar when clay is in short supply) and placed it at an incline to ensure water flows in the right direction.
In coordination with brickwork, we pitched stones on both sides of the spring's drainage channel. We then cemented and plastered each stone, forming the rub walls. These walls discourage people and animals from standing in that area, which could cause soil erosion and a clogged drainage area.
Plastering.
We then cemented and plastered both sides of the headwall and wing walls. These finishing layers reinforce the brickwork and prevent water in the reservoir from seeping through the walls. In turn, enough pressure builds in the reservoir box to push water out through the discharge pipe.
As the headwall and wing walls cured, we cemented and plastered the stairs and installed four tiles beneath the discharge pipe. The tiles protect the concrete from the falling water's erosive force while beautifying the spring and facilitating easy cleaning of the spring floor.
The final stage of construction is backfilling the reservoir box behind the discharge pipe. We cleared the collection box of any debris that may have fallen during construction. Then we redirected the temporary diversion channels back into the reservoir box, channeling water into this area for the first time. We closed off all of the other exits to start forcing water through the discharge pipe only.
Community children help collect large stones to backfill the reservoir box.
We filled up the reservoir area with the large, clean stones community members had gathered, arranging them in layers like a well-fitting puzzle. We covered the rocks with a thick plastic tarp to minimize potential contamination sources, then piled enough dirt on top to compensate for future settling.
Each community member transplanted grass as a sign of togetherness onto the backfilled soil to help prevent erosion. Finally, the collection area was fenced to discourage any person or animal from walking on it. Compaction can lead to disturbances in the backfill layers and potentially compromise water quality.
Community members transplanting grass.
The entire construction process took about two weeks of work and patience to allow the cement and plaster to finish curing. As soon as the spring was ready, people got the okay from our field officers to fetch water.
The completed spring.
We officially handed over the spring to mark the community's ownership of the water point. Happiness, thanksgiving, and appreciation were the order of the day, flowing in all directions. Community members were very excited and happy to see their new water source well protected. The elected officials gathered around the waterpoint with community members saying prayers for love and peace in the community.
Training on Health, Hygiene, and More
Together with the community, we found their preferred date for training while considering other community calendar events, such as the agricultural season and social events. We requested a representative group of community members to attend training to relay the information learned to the rest of their family and friends.
When the day arrived, facilitators Victor Musemi and Jonathan Mutai deployed to the site to lead the event. 29 people attended the training, including 19 women and 10 men. We held the training outside a community members home near the spring.
We covered several topics, including community participation in the project, leadership, and governance, personal and environmental hygiene, water handling and treatment, spring maintenance, dental hygiene, the ten steps of handwashing, disease prevention, and how to make and use handwashing stations.
The elected water committee.
During the leadership and governance session, we held an election for the newly formed water user committee leaders, who will oversee the maintenance of the spring. We also brainstormed income-generating activities. Community members can now start a group savings account for any future minor repairs to the spring and a cooperative lending group, enabling them to develop small businesses.
Learning the process of making soap was a highlight for participants. They witnessed the process with much excitement finding it difficult to imagine that soap can be manufactured locally using just reagents and water. During the mixing the majority of women participated and decided to form a group which will help the community make soap and sell it at an affordable price to empower themselves.
Isaac at the spring.
Farmer Isaac Martin, 20, shared, "The training has really added value to me. I have learned matters concerning hygiene and sanitation which are key important aspects of life. [The] soap making process is also an important aspect in life. I can also train others and be a good ambassador to others."
Conclusion
This project required a substantial collaboration between our staff, our partners, and the community members themselves. When an issue arises concerning the spring, the water user committee is equipped with the necessary skills to rectify the problem and ensure the water point works appropriately. However, if the issue is beyond their capabilities, they can contact our field officers to assist them.
Also, we will continue to offer them unmatchable support as a part of our ongoing monitoring and maintenance program. We have an ongoing commitment to walk with each community, cooperatively problem-solving when they face challenges of any kind: with functionality, seasonality, or water quality. With all these components together, we strive to ensure enduring access to reliable, clean, and safe water for this community.
With your contribution, one more piece has been added to a large puzzle of water projects. In our target areas, we're working toward complete coverage of reliable, maintained water sources within a 30-minute round trip for each community, household, school, and health center. With this in mind, search through our upcoming projects to see which community you can help next!